House renovation checklist in the order the work actually has to go in

A whole house renovation goes wrong in sequence more often than in workmanship. Almost every expensive mistake is a stage done out of order: plastering before the roof is watertight, a new kitchen before the rewire, floors laid before the heating is proved. The checklist that matters is not a list of jobs, it is the order they can be done in without undoing each other.

Get roofing quotes

A step-by-step home renovation checklist starts weathertight and dry

Roof, gutters, flashings, external walls, windows and any ground level moisture problem come before anything internal. This is the stage most often skipped because it is invisible in photographs, and it is the stage that ruins the rest when it is left. If damp is present, establish what kind it is before any treatment is bought, because the remedies for penetrating damp, rising damp and condensation are different and only one of them is usually needed.

Strip out, then structure, then first fix

Take out what is going, then form the openings, install the beams and complete any structural work, then run the services. First fix electrics, plumbing, heating pipework, waste and ventilation all happen while the walls are open. Anything that needs a chase in a wall, a hole through a joist or a duct to outside belongs here. Notifiable electrical work needs either building control or a competent person scheme certificate, so agree the route now rather than at the end.

Insulation, plaster and the drying time nobody plans for

Insulation goes in with the walls and roof open, and getting it continuous matters more than getting it thick. Then plaster, then the drying time, which is real and cannot be hurried without storing up cracking and paint failure. The households that suffer most are the ones that booked the decorator against a date rather than against a moisture reading.

Second fix, floors and snagging

Second fix electrics and plumbing, kitchen and bathroom, then floor finishes last so they are not lived on by trades. Keep a retention, walk the house with the builder at the end and write the snagging list together, and revisit it after a heating season, because the faults that appear in the first winter are the ones that tell you whether the fabric work was done properly.

1950s house renovation uk priorities: what this era usually needs

A house of that period has a predictable list, and the order matters more than the total. The roof covering is at or near the end of its life, so it is the first thing to price and the first thing to do. The walls are usually cavity but frequently unfilled, which is the cheapest measure in the house. The wiring and the consumer unit will be on their second or third life at best. Original steel or early timber windows will be single glazed and often painted shut. And the layout is the reason people buy these houses and the reason they renovate them, because the separate kitchen and dining room is the wall most owners want gone, which turns the job into a structural one. Materials of that era can also contain asbestos, so anything being broken out gets checked rather than guessed at.

Questions people ask about house renovation checklist

What is the most common ordering mistake?

Starting inside before the building is weathertight and dry. Every finish applied over an unresolved moisture problem has to be done twice.

When should the kitchen be chosen?

Early, because it determines the position of services, but it should be installed late, after plastering and drying.

Do I need building control for a renovation?

For structural alterations, new drainage, most electrical work, replacement windows and anything that changes fire escape, yes. Cosmetic work alone, no.

Is it worth living in the house during a full house renovation?

It is cheaper and slower. On a full renovation with a rewire and replastering it is rarely comfortable, and the programme usually stretches.

Sources

Get a roofing quote from contractors registered to sign off their own work

Free for property owners. Your details go to contractors covering your area, not to a call list. We may email you about this enquiry and similar services from this site; opt out any time, including from the first message.

Related answers

Get roofing quotesSearch the register